Hi Tim,
I hope you are doing well and I'm looking forward to our catch up.
Winten and I have been working on a special home at 25 Kimberly StreetVuacluse and we would like your assistance with the finlaising the project documentaion.
The project is a single residence, two levels over a basement, and we need yor assistance to produce and coordinate our constuction documentation in a timley manner.
The builders have commenced excavation on site.
You can find the relevant project files in the link below:
We agreed with the client and the builder on the following deadlines, subject to coordination with external consultants. Please see below:
Timeline
Package 1 - 19th of June (Two weeks)For Coordination Set
CC210 Series - Structural Setout
CC600 Series - Pool Details
CC220 Series - Wall Setout Plans and wall types
CC200 Series - Floor Plans suitable for CC2
CC300 Series - Elevations
CC400 Series - Sections
Package 2 - 3rd of July ( Two Weeks)
For Coordination Set